E5: San Francisquito Creek Flood Protection*
The project is led by the San Francisquito Creek Joint Powers Authority (SFCJPA), of which Valley Water is a member agency, in partnership with the U.S. Army Corps of Engineers (USACE).
Preferred project: A federal-state-local partnership
The project is to construct improvements along San Francisquito Creek from San Francisco Bay to just upstream of the Pop-Chaucer Bridge and additional detention of floodwaters upstream of Highway 280 to provide 1% (100-year event) flood protection, ecosystem restoration and recreational benefits to surrounding communities.
Local-state-funding-only partnership
Highway 101 to Pope-Chaucer Bridge
This stretch of the project will remedy channel constrictions and replace bridges at Newell Road and Pope/Chaucer streets to allow the channel to contain floodwaters of approximately 7,500 cubic feet per second, equivalent to approximately a 1.4% flood event (70-year event). Allowing this level of water to flow through the channel will protect approximately 3,000 parcels in Palo Alto from a flood event close to the February 1998 flood, the largest on record. Currently the channel can only convey approximately a 7% flood event (approximately a 15-year event).
Newell Road Bridge
The Newell Road bridge replacement, unlike the rest of the project elements in this stretch, is led by the City of Palo Alto, which has applied for funding through Caltrans’ Highway Bridge Program (HBP). The project has been programmed by Caltrans to fund approximately 89% of the total cost for replacing the Newell Road bridge, while the local match funds, approximately 11% of the total cost, will be funded by Valley Water through the Safe, Clean Water Program renewal. The City of East Palo Alto and the SFCJPA continue to provide input on the Newell Road bridge replacement.
The SFCJPA continues to pursue partnerships with federal, state and local agencies and grant opportunities for additional construction funding.
The San Francisquito Creek Joint Powers Authority (SFCJPA) is the official project lead and is ultimately responsible for the overall project design and for securing and finalizing permits and funding. Valley Water is one of the five-member agencies of the SFCJPA.
On December 31, 2022, the San Francisquito Creek overtopped its banks and flooded the nearby communities. The level of overtopping experienced did not match the predictive hydraulic models, prompting recalibration efforts and subsequently, a reevaluation of the Upstream Reach Project.
Upstream of Highway 101 Reach (Upstream Reach)
The SFCJPA’s design consultant is currently updating hydraulic models and re-evaluating project alternatives to account for unexpected flooding that occurred during winter 2022-23. The SFCJPA expects this alternatives analysis to continue through the rest of 2025. This report will evaluate potential actions that can be combined into alternatives to provide flood risk reduction up to 7,200 cfs level from Highway 101 to Middlefield Road.
Concurrently, the SFCJPA and USACE are continuing work on the CAP 205 program. The existing conditions model is complete, and now work has begun on the future without project (FWOP) model.
The design for the Newell Road Bridge was completed in March 2023, after which the City of Palo Alto completed right-of-way acquisition, selected a construction management consultant, and selected a contractor for construction. Early construction activities began in fall 2025. For more information, visit the city’s website.
Previous Updates
From 2017 to 2019, the SFCJPA developed an Environmental Impact Report for a smaller-scale project that addresses creek flooding similar to the 1998 flood, and is achievable within the funding constraints of the partner agencies. At its September 26, 2019 meeting, the SFCJPA Board unanimously certified the Project FINAL Environmental Impact Report, approved the project, and authorized the Executive Director to secure the permits, funding and land rights necessary to build it. The SFCJPA then began the lengthy process of acquiring permits from multiple agencies to construct the Upstream Reach of the Project.
The hydraulic model was recalibrated to incorporate the conditions observed during the storms that caused the creek’s banks to overflow on December 31, 2022. The SFCJPA completed the validation of initial findings through a 3rd party independent review and creek channel surveys in February 2024.
The SFCJPA entered into a Feasibility Cost Share Agreement (FCSA) with the USACE in the summer of 2021 and initiated the Continuing Authorities Program Section 205 (CAP 205) process. The draft USACE feasibility study report was completed in July 2022, and the final study report will be resumed when the USACE completes their validation of the recalibrated hydraulics model.
SFCJPA Board approved a Master Services Agreement with a design consultant on April 25, 2024. The consultant services include updating the project objectives and design criteria based on the recalibrated hydraulics model, and to reevaluate the alternatives listed in the Environmental Impact Report (EIR). The SFCJPA will resume preparing applications for regulatory permits to construct the Upstream Reach of the Project upon completion of reevaluating the EIR alternatives and selecting the preferred project alternative.
Bay to Highway 101 Reach (Downstream Reach) (Completed)
The flood protection features of the Bay to Highway 101 Reach of the Project are now complete. Improvements to this stretch of about one and a half miles of the creek constitute the necessary first step in an overall plan to provide more than 5,700 homes and businesses with creek flood protection. The Downstream Reach of the Project also provides improved access to trails.
The Operations and Maintenance Agreement between Valley Water, East Palo Alto, and the SFCJPA was executed by all parties in Fall 2021 which was then included in the final Operations and Maintenance Manual.
October 2025